New Doors shown by Colby Caid

We've had much construction this summer at our MHS.  The new roof membrane is attached. The new skylights have not arrived and should be installed in mid to late September. About half of the new doors/hardware that are being installed have arrived and the rest should be completed by mid to late September. This construction will be scheduled to not interrupt teaching and learning.

We are looking forward to starting our Facility Condition Assessment and Master Facility Plan with Wightman, our architects, soon.